Mercia Marina Canal Access, Derby
Development of Willington Lakes to form the Mercia Marina required the creation of a new connection canal to the nearby Trent and Mersey Canal. The road access to the site was raised over the new canal spur as it passes through a 17.5m long tunnel.
If you’d like to arrange training for your organisation about the features and benefits of our Arch and Portal Frame systems, please visit out Training page.
Products Supplied
- Design, manufacture and installation of the precast arch system to provide a 17.5m long, 8.4m span, 4.8m high access tunnel using ABM’s 25/40 Arch System. The structure was supplied in 7, 2.5m long three part sections.

Contractor
Designer
Client
Request a tailored quotation for your precast concrete needs. Our expert team is ready to provide you with a detailed and competitive quote, ensuring your project requirements are met with precision and efficiency.